Jump in time with us
Old rooms are transformed into modern interior design
(A fairy tale with 1001 pictures)
2015/2016
Removal of the interior panelling and hollowing out of the room shell.
February to March 2016
Lowering the cellar floor of the old vault by approx. 60 cm using a pickaxe and shovel.
December 2016 to January 2017
Lumber felling in your own forest. A lunar felling in winter after a beautiful autumn results in particularly dry and quiet wood.
January 2017 to August 2017
Dismantling of the roof, the farm building and parts of the house.
August 2017
Earthworks.
October to November 2017
Master builder work.
May to June 2018
Removal of walls and ceilings according to their numbering, reassembly after thorough cleaning and drying.
July to November 2018
Outside formwork and roof shingles.